Squaw Valley Mutual Water Company

Something Old, Something New: New twist on trenchless shows promise for California water company’s ability to avoid costly permitting process

Challenge
Burst and remove 3,000 feet of galvanized steel transmission line without damaging the new replacement pipe being installed in the same pull.

Solution
We custom engineered a solution using a steel cylinder slightly larger in diameter than the existing pipe, attached to the end of the pulling cable. As the ram pulled on the cable, the steel cylinder forced the old pipe through the ground, causing it to emerge in the exit pit. The extraction cage split the old pipe at the top as it emerged from the ground. This allowed the pulling cable to be diverted upward. The split pipe continued horizontally and was cut off and removed in short sections. The process continued until the entire original section of pipe had been removed and the HDPE replacement pipe was pulled into place. The project allowed the customer to avoid costly and time-consuming permitting processes, as well as disruption to the limited road network in its hilly location. View details.

Client:
Squaw Valley Mutual Water Company

Technology Utilized:
Monolithic BC20 hydraulic puller, duct rodder, 3/4-inch steel cable, hydraulic pump and resistance plates

Call (888) 883-8742 angle-down arrow-down arrow-right arrow-up-right bucket bubble checkmark cross droplet envelop facebook facebook22 fire folder google-plus instagram lamp linkedin location menu office phone play3 price-tag power quotes-left quotes-right spinner star-empty star-full star-half twitter user wrench yelp youtube ReviewsOpen Reviews